Photos released by the City of Oak Ridge and CNS Y-12 on Monday show the landslide that occurred next to the access road to the Oak Ridge Water Treatment Plant on Pine Ridge in February.
Last week, Oak Ridge Public Works Director Shira McWaters said it could cost an estimated $407,000 to repair the landslide, and the work should be complete by the end of July.
The water plant is on a ridge top above the main entrance to the Y-12 National Security Complex on Bear Creek Road. The landslide occurred next to the access road to the water plant on Saturday night, February 23. It’s the only access road to the water plant. It allows operations and maintenance workers to get to the water plant and deliver materials, equipment, and chemicals.
[Read more…]