The interior of the K-27 Building, which once enriched uranium through a process called gaseous diffusion, is pictured above on March 30, 2015. (DOE photo by Lynn Freeny)
Information from Oak Ridge Today and the January 2016 issue of “Advocate,” a publication of the Oak Ridge Site Specific Advisory Board
Demolition work could start early this year on the K-27 Building, the last of five gaseous diffusion buildings at the former K-25 site, now known as East Tennessee Technology Park or Heritage Center. The giant buildings were once used to enrich uranium for nuclear weapons and nuclear power plants, starting during World War II and continuing through the Cold War.
Deactivation work continues at the K-27 Building, preparing it for demolition. At the beginning of December, deactivation of the building was more than 96 percent complete. Workers continue to remove transite paneling on the building, but that job is 80 percent complete.
Sue Cange, manager of the U.S. Department of Energy’s Oak Ridge Office of Environmental Management, has previously said that demolition work could start on the building in early 2016 and be complete by the end of the year.
Demolition work on the former K-31 Building, the fourth of the five buildings to be demolished, was completed in June. [Read more…]