Solar-powered pedestrian warning signs and new pavement markings could be installed at three crosswalks on Melton Lake Drive.
The crosswalk improvements are proposed at Amanda Drive, Emory Valley Road, and Rivers Run. They will be considered by Oak Ridge City Council on Monday night.
The Oak Ridge city staff has recommended awarding a roughly $38,000 contract to First Place Finish of Oak Ridge for the crosswalk work, which could start in April and be completed in four to six weeks. The bid was the lowest of four received, City Engineer Steven R. Byrd said in a memo to City Manager Mark S. Watson.