The following is an edited version of a question-and-answer session with John Eschenberg, federal project director for the proposed Uranium Processing Facility at the Y-12 National Security Complex. Federal officials said last fall that the UPF could be larger than originally planned to make sure all the building’s equipment fits inside.
Q: What is the status of the UPF redesign?
A: UPF is currently at 66 percent of design completion. Once 90 percent design completion is achieved, we will submit a Critical Decision-2 (CD-2) package to headquarters for approval that will contain the complete cost and schedule baseline for UPF. This process, which involves both an independent cost estimate and an external independent review, will likely take several weeks to complete.
The cost range for UPF is unchanged: $4.2 billion-$6.5 billion.