Council to consider zoning district that could allow motorsports park

Horizon-Center-Motorsports-Track-6-Feb-11-2020
Part of the site where a motorsports park could be built on the back side of Horizon Center in west Oak Ridge is pictured above on Tuesday, Feb. 11, 2020. (File photo by John Huotari/Oak Ridge Today)

The Oak Ridge City Council on Monday will consider a zoning ordinance amendment that could allow a motorsports park.

A motorsports park has been proposed at the Horizon Center in west Oak Ridge. The proposal has both supporters and detractors.

The zoning ordinance amendment being considered by Council at 7 p.m. Monday, February 8, does not endorse that specific proposal. Instead, it would create a new zoning district, the special recreation district, which could be used for large-scale recreation and entertainment developments.

A motorsports park would be one of the permitted uses in the new zoning district, if it is approved. Other permitted uses would be an amphitheater, athletic facility, fairground, amusement park, and zoo.

[Read more…]

Construction of new water plant could start in May, be complete next year

An image showing the interior of the proposed new 16-million-gallon-per-day water treatment plant at the City of Oak Ridge water intake on the Clinch River south of Bethel Valley Road. (Image courtesy of Jacobs Engineering Group and the City of Oak Ridge)

Construction of the new water plant at the city’s water intake on the Clinch River could start in May and be complete in December 2022, according to a proposed schedule presented to Oak Ridge City Council.

The Council on Monday will consider a construction administration contract for the new water plant, which would be south of Bethel Valley Road. It would be able to treat 16 million gallons of water per day.

If approved Monday, the professional engineering services agreement would be with Jacobs Engineering Group Inc. of Knoxville. The contract would be valued at up to about $1.88 million. It would be for construction administration and observation of the construction of the new water treatment plant and a main transmission line.

Approval of the agreement with Jacobs Engineering on Monday could be contingent upon the city’s ability to use Drinking Water State Revolving Funding, which is pending approval, according to the resolution to be considered by Council.

[Read more…]

TVA asks for public comments about proposed nuclear reactor site

TVA Clinch River Site
The Clinch River Site in west Oak Ridge is pictured above. The road running from bottom to top on the right (east) side of the Clinch River connects to Bear Creek Road in southwest Oak Ridge. Highway 58 is off to the top left of the photo and the Heritage Center is to the north. (Photo courtesy TVA)

The Tennessee Valley Authority is asking for public comment about a proposal to build one or more small or advanced nuclear reactors in west Oak Ridge.

The reactors would be on the Clinch River Nuclear Site, near the Clinch River and south of Heritage Center (the former K-25 site) in Roane County.

The reactors could be advanced or small modular nuclear reactors. They would have a maximum total electrical output of 800 megawatts. They would be smaller than traditional nuclear power plants, and they would produce less power.

Oak Ridge Today has previously reported that the reactors could provide enough electricity to power several cities the size of Oak Ridge

[Read more…]

Tower rebuilding complete, South Illinois re-opened overnight

The replacement of a large high-voltage transmission tower was completed Sunday, Jan. 24, 2021, and South Illinois Avenue re-opened to traffic at about midnight. (Photo courtesy Tennessee Valley Authority)

The rebuilding of a large high-voltage transmission tower in Oak Ridge was completed Sunday, and South Illinois Avenue re-opened to traffic at about midnight.

The 155-foot steel lattice tower that had to be replaced was knocked over when a pickup truck crashed into it at about 4:15 p.m. Friday. The tower, which is at Union Valley Road, carries high-voltage Tennessee Valley Authority transmission lines and city transmission and distribution lines.

The four-lane road, the main connection between Oak Ridge and Knox County, was closed for about two days after the crash while crews removed and replaced the damaged transmission tower.

TVA said the crash also caused damage to three smaller structures, and they were repaired.

[Read more…]

South Illinois Avenue to re-open by midnight

South Illinois Avenue is expected to re-open by midnight Sunday, Jan. 24, 2021, near the University of Tennessee Arboretum after being closed for more than two days because of a large high-voltage transmission tower that was knocked over in a crash on Friday. The repair work is pictured above on Sunday. (Photo courtesy City of Oak Ridge)

South Illinois Avenue is expected to re-open by midnight near the University of Tennessee Arboretum after being closed for more than two days because a large high-voltage transmission tower was knocked over near the road in a crash on Friday. The road re-opening is expected to occur before the Monday morning commute.

Power is still out for a small southeast portion of the city near the crash site, including the University of Tennessee Arboretum, the City of Oak Ridge said Sunday evening.

The single-vehicle crash into the Tennessee Valley Authority steel lattice transmission tower was reported at Union Valley Road at about 4:15 p.m. Friday. That section of the four-lane road, also known as State Route 62 and Pellissippi Parkway, has been closed since shortly after the crash. The road is the main connection between Oak Ridge, Knox County, and Knoxville.

TVA and the Oak Ridge Electric Department worked over the weekend to replace the damaged transmission tower, which carries TVA and Oak Ridge power lines. The repair crews had help from the Oak Ridge Police Department and Oak Ridge Public Works Department. It was a complex emergency repair, the City of Oak Ridge said.

[Read more…]

South Illinois could re-open Monday

Crews repair the damage to the Tennessee Valley Authority distribution system after a pickup truck crashed into a high-voltage steel lattice transmission tower, causing widespread power outages in Oak Ridge and the surrounding area on Friday, Jan. 22, 2021. (Photo by John Huotari/Oak Ridge Today)

Work to repair the damage to a Tennessee Valley Authority transmission tower knocked over in a crash on Friday could be complete in time to open South Illinois Avenue (State Route 62) in time for the Monday morning commute, a spokesperson said Sunday.

However, the schedule could be affected by weather and any potential drilling delays.

TVA spokesperson Scott Brooks said heavy equipment, materials, and workers, as well as safety and engineering plans, are required to replace the large high-voltage steel lattice tower that was knocked over by a pickup truck Friday afternoon. The safety and engineering were completed Friday evening, Brooks said.

“The heavy equipment, materials, and manpower needed to perform the work are either on site or en route,” he said. “We currently expect the work to be completed in time for Highway 62 to be open for the Monday morning commute. Risks to that schedule are weather and potential drilling delays due to the topography (i.e. rock).”

[Read more…]