With a pre-application deadline this Wednesday, the Oak Ridge Industrial Development Board agreed last week to commit $750,000 to a project to increase the electrical capacity at Horizon Center Business Park if the city gets a matching grant from the Tennessee Valley Authority.
The project, which would add 14 megawatts to the park’s electrical capacity with the potential to add more later, would extend power from a substation on Blair Road in west Oak Ridge to the edge of Lot 5 on the back side of Horizon Center. It would install 13 kilovolt lines on poles that could hold 69 kilovolt lines later. [Read more…]