Conditions are subject to change, but current plans call for starting construction on a general aviation airport at Heritage Center, the former K-25 site, in 2018. The current estimate range says the airport could cost between $30 million and $40 million, officials said Wednesday.
Work on an airport master plan is just starting, and it could take 12 months to complete, said Bill Marrison, president of the Metropolitan Knoxville Airport Authority. He said that plan will provide more details on subjects like cost and schedule.
The Oak Ridge airport would the third for the MKAA, which would own the site. The other two are McGhee Tyson in Blount County and Downtown Island in Knoxville.
Marrison said the Oak Ridge airport would be a reliever airport and help relieve congestion at the other two airports. He said McGhee Tyson is at capacity and there is no hangar space available, and Downtown Island has 100 people on its waiting list. [Read more…]