Work began in June to build the Mercury Treatment Facility at the Y-12 National Security Complex.
The Mercury Treatment Facility will allow the U.S. Department of Energy to clean up and demolish several large Y-12 buildings that used mercury to separate lithium for nuclear weapons during the Cold War in the 1950s and 1960s. The facility is expected to help reduce the amount of mercury in East Fork Poplar Creek, which flows through Oak Ridge.
DOE announced in December that it had awarded a $91 million contract to build the Mercury Treatment Facility. The contract, which could be in place for up to four years, was awarded to APTIM-North Wind Construction JV LLC.
A groundbreaking was held at the site in November 2017, and site preparations were completed by December 2018.
[Read more…]