Submitted
The Y-12 National Security Complex flipped the switch on a new era as crews finalized the process of moving the entire site’s electrical supply to the new Pine Ridge substation.
In June, the Building 9204-02 (Beta 2) and Building 9201-01 (Alpha 1) electrical feeds were disconnected from the Elza-1 substation, marking the final load transition to Pine Ridge.
The new substation was built as one of seven Uranium Processing Facility Project subprojects. Designed and built by the Tennessee Valley Authority, Pine Ridge substation construction began in 2017 and was completed in 2020 at a cost of $60 million. The project team received the U.S. Department of Energy Secretary’s Project Management Achievement Award for finishing $13 million under budget and six months ahead of schedule. It is a 70-MVA (mega volt amp) facility and includes:
- 161-kilovolt (kv) switchyard,
- 13.8-kv power transformers,
- TVA switch house,
- DOE/National Nuclear Security Administration power distribution center, and
- 161-kv transmission lines.
New substation will serve Y-12, UPF
The Pine Ridge substation now fully services both Y-12 and the UPF project. UPF is one of DOE’s largest construction projects and investments in Tennessee since the Manhattan Project.
“This is a huge win for Y-12,†said Tim Hutson, director of Y-12 Utilities Management. “It positions us well, from an electrical distribution perspective, to serve the people and the mission of Y-12 for the next two to three decades.â€
The original Elza-1 was completed in 1952. Then, it was responsible for providing uninterrupted power to operate the site. As the main power feed for Y-12, it was rebuilt in the 1990s.
“The Elza-1 substation was oversized for the current Y-12 mission,†Hutson said. “Elza-1 is a 300MVA substation. Pine Ridge is 70 MVA.â€
The smaller substation is a win-win for the site, according to Hutson. “In addition to cost- and risk-reduction advantages, there is an approximate $30 million reduction in deferred costs, as well as significant decreased environmental and safety risks.â€
End of an era approaching
The final phase of the transition is quickly approaching.
“We can see the end of this effort in the next few months,†Hutson said. “This will mark the end of an era for the Elza-1 substation. It will be cold and dark by October, when TVA begins the process of transitioning the Bull Run feed from Elza-1 to Pine Ridge.â€
“Looking back, this has been a huge effort,†Hutson said. “It has taken a lot of people to make this happen, involving multiple organizations including Mission Engineering, the Project organization, our subcontract partners, federal customers, the UPF project, and TVA. This has been an exciting time.â€
More information will be added as it becomes available.
Most news stories on Oak Ridge Today are free, brought to you by Oak Ridge Today with help from our advertisers, contributors, and subscribers. This is a free story. Thank you to our advertisers, contributors, and subscribers. You can see what we cover here.
Do you appreciate this story or our work in general? If so, please consider a monthly subscription to Oak Ridge Today. See our Subscribe page here. Thank you for reading Oak Ridge Today!
Alternatively, you can donate to support our work here. Thank you for your support!
Copyright 2022 Oak Ridge Today. All rights reserved. This material may not be published, broadcast, rewritten, or redistributed.
Leave a Reply