• About
    • About Us
    • What We Cover
  • Advertise
    • Advertise
    • Our Advertisers
  • Contact
  • Donate
  • Send News

Oak Ridge Today

  • Home
  • Sign in
  • News
    • Business
    • Community
    • Education
    • Government
    • Health
    • Police and Fire
    • U.S. Department of Energy
    • Weather
  • Sports
    • High School
    • Middle School
    • Recreation
    • Rowing
    • Youth
  • Entertainment
    • Arts
    • Dancing
    • Movies
    • Music
    • Television
    • Theater
  • Premium Content
  • Obituaries
  • Classifieds

Q&A: John Eschenberg on Uranium Processing Facility at Y-12

Posted at 3:53 pm January 21, 2013
By John Huotari Leave a Comment

Uranium Processing Facility

The proposed Uranium Processing Facility at the Y-12 National Security Complex. (Image courtesy of B&W Y-12)

The following is an edited version of a question-and-answer session with John Eschenberg, federal project director for the proposed Uranium Processing Facility at the Y-12 National Security Complex. Federal officials said last fall that the UPF could be larger than originally planned to make sure all the building’s equipment fits inside.

Q: What is the status of the UPF redesign?

A: UPF is currently at 66 percent of design completion. Once 90 percent design completion is achieved, we will submit a Critical Decision-2 (CD-2) package to headquarters for approval that will contain the complete cost and schedule baseline for UPF. This process, which involves both an independent cost estimate and an external independent review, will likely take several weeks to complete.

The cost range for UPF is unchanged: $4.2 billion-$6.5 billion.

National Nuclear Security Administration project staff members, with the assistance of independent industry experts, evaluated the additional engineering efforts required to resolve UPF’s space challenge, and as a result, they are proceeding with finalizing the design.

Q: How does the progress on the current design compare to the progress before the changes?

A: The UPF design is at 66 percent. It was at 75 percent before the design changes.

Q: When will the design be at 90 percent?

A: UPF is currently reworking the design cost and schedule plan submitted to NNSA to address some additional cost and schedule elements requested by NNSA. Following the re-submittal of the total project design cost and schedule plan, the project will be better prepared to determine when 90 percent design completion will be achieved.

Q: When will site readiness work start?

A: NNSA is expected to approve the UPF project’s site readiness Critical Decision package soon.  With this approval, the UPF project team will have the authorization to issue awards and begin work on site. Initial awards will be issued by plant contractor B&W Y-12 for electrical demolition and establishing a wet spoils area for unusable soil, followed by a contract award by the U.S. Army Corps of Engineers for the extension of Bear Creek Road and associated potable water lines.

Plans call for starting the site readiness work this winter. This will include preliminary work to relocate some of the existing utilities and Bear Creek Road.

Q: How many critical decisions (CDs) are left before the “big CD-2 package?” What is the number of the site readiness critical decision, and what CD comes after that?

A: The U.S. Department of Energy uses critical decisions to authorize proceeding to different phases of a project. The next CDs on UPF will establish the formal commitment on cost and schedule (CD-2), and allow the construction activities to begin (CD-3).

Furthermore, NNSA has subdivided the initial work at the Y-12 site into manageable scopes of work to allow for the maximum flexibility in contracting for that work. Each of these sub-projects have their own CDs (CD-2 and 3) before construction starts. There are three sub-projects (site readiness, site preparation, and the west end protected area reduction (WEPAR)) that should be accomplished before the CD-2 for the entire UPF project is finalized.

Site readiness will be the next CD approval on UPF.

***

The 350,000-square-foot UPF would replace four old buildings at Y-12, part of a years-long effort to update the 811-acre site, consolidate operations, and cut the plant’s high-security footprint from 150 acres to 15. Y-12 was built to enrich uranium during World War II as part of the top-secret Manhattan Project. The UPF would be the single largest post-war investment by the government in Tennessee.

This Q&A was conducted via e-mail with the help of Bridget Correll Waller, UPF strategic communications manager.

Filed Under: National Nuclear Security Administration, Top Stories, U.S. Department of Energy, Y-12 National Security Complex Tagged With: CD-2, CD-3, critical decision, John Eschenberg, National Nuclear Security Administration, NNSA, site readiness, U.S. Department of Energy, UPF, UPF design, UPF redesign, uranium processing facility, Y-12 National Security Complex

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

More U.S. Department of Energy News

Kairos Power begins construction on demonstration reactor​

Kairos Power has started construction on a test nuclear reactor in west Oak Ridge. The Hermes Low-Power Demonstration Reactor is the first of its type to be approved for construction by the U.S. Nuclear Regulatory … [Read More...]

Availability of the draft environmental assessment for off-site depleted uranium manufacturing (DOE/EA-2252)

The U.S. Department of Energy (DOE) National Nuclear Security Administration (NNSA) announces the availability of a Draft Environmental Assessment (EA) for Off-Site Depleted Uranium Manufacturing, which analyzes the … [Read More...]

Manhattan Project Park: Walk through Wheat

You can walk through Wheat with a National Park Service ranger on Saturday, July 13, and learn more about the history of this community before the Manhattan Project. Wheat was in an area that is now west Oak Ridge, … [Read More...]

Crews preparing for first demolition of uranium enrichment building at Y-12

From U.S. Department of Energy "EM Update" email newsletter U.S. Department of Energy Office of Environmental Management crews at Oak Ridge are moving closer toward completing the first-ever demolition of a former … [Read More...]

K-25 cleanup shifting to groundwater

Crews are expected to finish remediating soil, reversing or stopping environmental damage at the former K-25 site in west Oak Ridge this year, and federal cleanup managers are shifting their focus to groundwater. It's … [Read More...]

More DOE

Recent Posts

  • Flatwater Tales Storytelling Festival Announces 2025 Storytellers
  • Laser-Engraved Bricks Will Line Walkway of New Chamber Headquarters
  • Democratic Women’s Club to Discuss Climate Change, Energy and Policy
  • Estate Jewelry Show at Karen’s Jewelers Features Celebrity Jewelry
  • Keri Cagle named new ORAU senior vice president and ORISE director
  • ORAU Annual Giving Campaign exceeds $100,000 goal+ORAU Annual Giving Campaign exceeds $100,000 goal More than $1 million raised in past 10 years benefits United Way and Community Shares Oak Ridge, Tenn. —ORAU exceeded its goal of raising $100,000 in donations as part of its internal annual giving campaign that benefits the United Way and Community Shares nonprofit organizations. ORAU has raised more than $1 million over the past 10 years through this campaign. A total of $126,839 was pledged during the 2024 ORAU Annual Giving Campaign. Employees donate via payroll deduction and could earmark their donation for United Way, Community Shares or both. “ORAU has remained a strong pillar in the community for more than 75 years, and we encourage our employees to consider participating in our annual giving campaign each year to help our less fortunate neighbors in need,” said ORAU President and CEO Andy Page. “Each one of our employees has the power to positively impact the lives of those who need help in the communities where we do business across the country and demonstrate the ORAU way – taking care of each other.” ORAU, a 501(c)(3) nonprofit corporation, provides science, health and workforce solutions that address national priorities and serve the public interest. Through our specialized teams of experts and access to a consortium of more than 150 major Ph.D.-granting institutions, ORAU works with federal, state, local and commercial customers to provide innovative scientific and technical solutions and help advance their missions. ORAU manages the Oak Ridge Institute for Science and Education (ORISE) for the U.S. Department of Energy (DOE). Learn more about ORAU at www.orau.org. Learn more about ORAU at www.orau.org. Like us on Facebook: https://www.facebook.com/OakRidgeAssociatedUniversities Follow us on X (formerly Twitter): https://twitter.com/orau Follow us on LinkedIn: https://www.linkedin.com/company/orau ###
  • Children’s Museum Gala Celebrates the Rainforest
  • Jim Sears joins ORAU as senior vice president
  • Oak Ridge Housing Authority Receives Funding Assistance of up to $51.8 Million For Renovating Public Housing and Building New Workforce Housing
  • Two fires reported early Friday

Search Oak Ridge Today

Copyright © 2025 Oak Ridge Today