UCOR has finished installing permanent electrical equipment at the 3026 hot cells facility at Oak Ridge National Laboratory.
This action completes all scheduled tasks under the 3026 Hot Cells Transition and Stabilization Phase, the U.S. Department of Energy Oak Ridge Office reported in the December issue of Public Involvement News.
UCOR took over the 3026 Hot Cells project at the request of DOE. The stabilization activities were con- ducted to help “downgrade” the facility from a Hazard Category 3 nuclear facility to a radiological facility, the Oak Ridge Office said. This downgrade, which has been approved by DOE, will make the facility less costly to maintain.
UCOR is DOE’s cleanup contractor in Oak Ridge.