But it could also save $1 billion through on-site disposal, officials say
A new landfill that would hold waste from cleanup work at federal sites in Oak Ridge could cost $1 billion, a project manager said Wednesday. That start-to-finish estimate includes construction and 23 years of operations.
But federal officials said the new landfill could save $1 billion in on-site versus off-site costs. That’s because the waste would be disposed on site and wouldn’t have to be shipped out of town, possibly to other states such as Nevada and Utah.
Saving money through on-site disposal could, in turn, accelerate the cleanup work at Oak Ridge National Laboratory and Y-12 National Security Complex, said Laura Wilkerson, federal project director for the Y-12 National Security Complex in the Oak Ridge Office of Environmental Management.
The new landfill, the Environmental Management Disposal Facility, would be built on Bear Creek Road west of the Y-12 National Security Complex near another landfill that is already in use and has been operating since 2002.
That earlier 43-acre, six-cell landfill is known as the Environmental Management Waste Management Facility. It has a capacity of 2.18 million cubic yards—about 872,000 pickup truck loads—and it is roughly 66 percent full. It’s expected to be filled by the remaining cleanup work at the East Tennessee Technology Park, also known as the former K-25 site, sometime around 2023. That’s assuming the cleanup program is funded at about $420 million per year.
Wilkerson said the remaining cleanup work at the Y-12 National Security Complex and Oak Ridge National Laboratory will require the ability to dispose of roughly as much waste as the EMWMF will hold.
“We will need additional capacity if we are to complete the cleanup of ORNL and Y-12,†Wilkerson told the Oak Ridge Site Specific Advisory Board on Wednesday. The SSAB is a volunteer group that provides recommendations to the U.S. Department of Energy environmental cleanup program.
The EMDF is projected to have a capacity of about 2.4 million cubic yards. Wilkerson said 16 sites were considered as possible locations. Among the advantages of the site in East Beer Creek Valley near Y-12:
- Access to the EMDF would be controlled through Y-12.
- The site is isolated from the public and has roads to Y-12 and ORNL.
- It’s a historic and current waste management area.
- There is already infrastructure in place at the EMWMF.
Like the EMWMF, the EMDF would have six disposal cells that could be built on an as-needed basis. The main difference between the new and old facilities is a stream. The EMDF will have to be engineered around that.
Federal officials hope to have what is known as a record of decision by 2016. Wilkerson said design work could begin in earnest this year or next, and site preparation and construction could start in 2019. The first cells could open in 2022.
There is a 25 percent capacity contingency built into the proposed facility.
Dave Adler, who is in charge of the reindustrialization program in DOE’s Oak Ridge Office of Environmental Management, said the scope of the cleanup program has grown significantly, but the projections for the EMWMF bore out pretty well.
Officials have a “high degree of confidence†that the capacity of the EMDF will be a little more than is needed, Adler said. He said there won’t be many so-called legacy buildings left after these cleanup projects are completed, and those that will be left have enduring missions.
Wilkerson said the primary cleanup effort was at ETTP when the EMWMF was built, with some buildings at Y-12 and ORNL. But now there are more excess facilities at ORNL and Y-12, and the amount of projected waste has gone up, which explains the need for the new landfill.
K-25, Y-12, and ORNL, once known as X-10, were all built in the 1940s during the top-secret Manhattan Project in World War II. Many older buildings have been torn down or are being torn down, and the sites are being modernized or, in the case of K-25, converted to industrial use.
Wilkerson said she thinks the “bulk of the really old facilities…have been accounted for†in the planning for EMDF.
She there will be an opportunity for the public to comment on the EMDF. The city of Oak Ridge has hired a firm to help collect public input, Wilkerson said.
Federal officials estimate they’ve already saved about $500 million in off-site disposal costs using the EMWMF. They said they’ve helped maintain jobs in Oak Ridge, eliminated an estimated 130,000,000 driving miles, and reduced handling and worker exposures.
Wilkerson said the on-site disposal is key to the program’s success.
About 86 percent of the waste from the former 44-acre K-25 Building, once the world’s largest under one roof, was taken to EMWMF. The same is true for the K-33 Building. Both buildings were at ETTP, the former K-25 site.
The landfill waste can include low-level radioactive waste, such as building debris, soil with low-level contamination, personal protective gear, scrap equipment, and asbestos. It does not include higher-activity waste, spent fuel, or transuranic waste.
Wilkerson said the EMWMF has operated safely for close to 13 years, and there has been no migration of contaminants detected through quarterly groundwater monitoring.
She said the new landfill needs to be ready at least 18 months before the existing facility reaches its capacity. The work to be completed before then includes site characterization, design, procurement, and public involvement. Construction work would have to start by 2019 to have the EMDF completed by 2022, Wilkerson said.
See Wilkerson’s presentation to the SSAB here:Â Laura Wilkerson Waste Disposal Presentation to ORSSAB Feb 11 2015
Joseph Lee says
This is good news for Oak Ridge, Anderson County, Roane County, Tennessee and The United States of America. Thank you DOE.